Allied Mills Factory

Sector

Industrial

Location

Tullamarine, VIC

Allied Mills Factory

Stats

$5M

Project value

25

Weeks to build

Details

Client

Allied Mills

Subsector

Food / Beverage

Completed

2014

Share

Contributors

Client

Project Manager

BECA

Architect

Engineer

Team Leader

Dan Casey

Team Leader

Dan Casey

Project Manager

BECA

Architect

Watson Young

Engineer

BECA

Hutchies was contracted by Allied Mills to refurbish its existing facility in Tullamarine to make way for new TS3 independent processing equipment. The works were completed in 12 stages.

The bakery facility remained fully operational throughout the duration of the works; 24 hours a day, Monday to Friday.

#Find out more about this project