Moranbah Airport

Sector

Civil & Infrastructure

Location

Moranbah, QLD

Moranbah Airport

Stats

$16M

Project value

30

Weeks to build

2970m²

Built area

Details

Client

BHP Billiton Mitsubishi Alliance (BMA)

Subsector

Transport

Completed

2012

Share

Contributors

Client

Architect

Civil Engineer

Electrical Engineer

Team Leader

Michael Michell

Photographer

Team Leader

Michael Michell

Architect

Vabasis

Civil Engineer

ADG Engineers

Electrical Engineer

ADG Engineers

Photographer

Angus Martin

The $16M Moranbah Airport Extension and airside works were undertaken on a design & construct basis and consisted of 2970m² of airport terminal set up for dual operation by BMA in one half, with the other half commissioned for public use. The building houses single check-in and baggage handling facilities with dual arrival and departure facilities. Working to an immovable deadline set by Civil Aviation Safety Authority, the facility was constructed in strict accordance with aviation security requirements.

Meeting the fixed deadline became quite challenging due to development approval issues, however, Hutchinson Builders was able to claw back three months in order to meet all critical dates and final deadline.